Timing Pre-Listing Work Around Palm Beach Season Construction Rules
From November 1 to April 30, the Town of Palm Beach allows construction only on weekdays, stops it entirely from December 24 through January 1, and bans jackhammers, pile drivers and demolition outright. An owner who wants a finished house on the market in January has a short and shrinking window to schedule the roof, the pool, the windows and the paint. This guide lays out the construction rules as the Town Code reads in October 2026 and shows how to build the work calendar backward from a listing date.
Seller Answer in Brief
In the Town of Palm Beach, schedule any noisy, exterior or permitted pre-listing work to finish by October 31. From November 1 through April 30, construction is limited to weekdays from 8:00 a.m. to 5:00 p.m., with no site noise before 9:00 a.m., no Saturday work, no work from December 24 through January 1, and no jackhammers, pile drivers or demolition. Small repairs are not exempt if they need a permit or construction tools.
- The winter season now runs November 1 to April 30 under Town Code sec. 42-199(b), as amended by Ordinance No. 021-2025 (October 14, 2025) and Ordinance No. 18-2026 (July 14, 2026).
- From November 1, 2026 to April 30, 2027, 117 of 181 calendar days are permitted construction days, by our count from the Town holiday sheet revised July 16, 2026.
- Demolition of structures is prohibited and no demolition permits are issued from November 1 to April 30 (sec. 18-112). Interior demolition is allowed only if demolition and debris removal take three days or less.
- Dredges, hammer-driven pile drivers, dry sandblasting machines and jackhammers are banned in the same period (sec. 42‑198).
- Construction work is defined as permitted work or work using construction, drilling or demolition tools, so many “small” jobs fall under the hours.
- Minor permits must pass final inspection within 12 months of issuance (sec. 18-238), which matters for a buyer’s permit search.
In this guide
- What Palm Beach allows on a winter weekday
- When the Palm Beach construction season starts now
- Why small repairs are not exempt from the construction rules
- The winter machinery and demolition bans
- Counting the working days in the 2026 to 2027 season
- Building the schedule backward from a Palm Beach listing date
- Town review steps that set the start date
- Site rules that follow the house onto the market
- Permit clocks and what a buyer’s search will show
- Condominium and co-op apartments on the island
- Worth Avenue, shutters and the lawn crew
- Choosing between an in-season launch and a summer finish
- Frequently asked questions
What Palm Beach allows on a winter weekday
A contractor working on the island between November 1 and April 30 has a nine-hour day at most, and only the last eight of those hours can be loud. Town Code sec. 42-199(b) sets the winter schedule: work allowed from 8:00 a.m. to 5:00 p.m. Monday through Friday, arrival on site no earlier than 7:30 a.m., quiet interior work only from 8:00 to 9:00 a.m., and no site noise before 9:00 a.m. (Town of Palm Beach Code, ch. 42, art. V).
The footnote to that table carries most of the weight. During the winter season, all construction work is prohibited on Saturdays, Sundays, Town-observed holidays, the day before and the day after Thanksgiving, and from December 24 through January 1. The December 24 to January 1 ban came from Ordinance No. 7-2025, adopted July 9, 2025, and the Town’s own holiday sheet marks each of those dates “No Construction Work Permitted per Ord. No 7-2025” (Town of Palm Beach, Working Hours for Construction, rev. July 16, 2026).
The summer schedule is looser, and the contrast is the reason timing matters. From May 1 through October 31, the code text allows weekday work from 8:00 a.m. to 6:00 p.m. and Saturday work from 9:00 a.m. to 5:00 p.m. The Town Council can change those hours temporarily by resolution under sec. 42-199(e)(5), and it has. The Town’s published sheet for May 1 through October 31, 2026 shows weekday work from 7:30 a.m. to 5:30 p.m., arrival from 7:00 a.m. and no site noise before 8:30 a.m., citing Resolution No. 155-2025 and Resolution No. 041‑2026.
| Rule | Winter, Nov 1 to Apr 30 | Summer 2026, May 1 to Oct 31 (Town sheet) |
|---|---|---|
| Weekday work allowed | 8:00 a.m. to 5:00 p.m. | 7:30 a.m. to 5:30 p.m. |
| Earliest arrival on site | 7:30 a.m. | 7:00 a.m. |
| No site noise before | 9:00 a.m. | 8:30 a.m. |
| Saturday | No work | 9:00 a.m. to 5:00 p.m., quiet work only; no deliveries, concrete pours or sawing, demolition or heavy equipment |
| Sunday and Town holidays | No work | No work |
| Day before and after Thanksgiving | No work | Not applicable |
| December 24 to January 1 | No work | Not applicable |
| Jackhammers, pile drivers, dredges, dry sandblasting | Prohibited (sec. 42‑198) | Allowed within hours |
| Demolition of structures | Prohibited, no permits issued (sec. 18‑112) | Allowed with permit |
Sources for the table: Town Code secs. 42-198, 42-199 and 18-112 as posted on Municode (Supplement 30, Update 2, online October 5, 2026), and the Town working hours sheet revised July 16, 2026. The summer column reflects temporary resolutions for 2026 only. What applies after October 31, 2026, and again in May 2027, is whatever the code and any new resolution say at that time. Before booking summer 2027 work, ask the Planning, Zoning and Building Department, (561) 838-5431, for the hours sheet in force for that summer. A later start or an earlier stop each day changes how many crew hours fit between May 1 and an autumn listing date.
For a seller, the practical reading is simple. A Saturday in October is a working day for a crew. A Saturday in November is not. A weekday in late December may look open on a contractor’s calendar and still be closed on the island.
When the Palm Beach construction season starts now
The season starts November 1. Owners who renovated on the island a few years ago may remember a later start, and that memory is now wrong in a way that can cost a month.
The amendment history printed under sec. 42-199 shows the sequence. Ordinance No. 021-2025, adopted October 14, 2025, amended both the machinery ban in sec. 42-198 and the hours in sec. 42-199. Before that change, Palm Beach Daily News reporting on the proposal described the in-season limits as starting on the first Monday after Thanksgiving, and the ordinance moved that start to the beginning of November, extending the heavy equipment ban by close to a month (Palm Beach Daily News via Yahoo News, secondary source). The codified text now reads “Beginning on November 1, and until April 30 of each year.” Ordinance No. 18-2026, adopted July 14, 2026, amended secs. 42-197, 42-198 and 42-199 again.
Three practical consequences follow for a seller in the Town of Palm Beach.
Contractor calendars may still assume a late-November start
A roofer or pool contractor who works across Palm Beach County may plan noisy work for the first three weeks of November out of habit. Ask in writing which phases need jackhammers, chipping hammers, sandblasting or demolition, and get those phases on the calendar before November 1.
The first winter week now overlaps Veterans Day and Thanksgiving
November 2026 has 21 weekdays. Veterans Day on November 11, the Town-observed day before Thanksgiving on November 25, Thanksgiving on November 26 and the Town-observed day after on November 27 remove four of them, which leaves 17 working days in a month that used to be mostly summer hours.
October is the last month with Saturdays
From October 9 through October 31, 2026 there are 16 weekdays and 4 Saturdays left under summer rules. After that, the next Saturday work day on the island is in May 2027.
The Town publishes a revised hours sheet when the rules change, and the July 16, 2026 revision lists Ordinance Nos. 26-2021, 4-2022, 7-2025, 21-2025 and 18-2026 and Resolution Nos. 155-2025, 041-2026 and 79-2026. Read the date on the sheet before relying on it. The Code Enforcement Department at 345 South County Road, (561) 227-7080, and the Planning, Zoning and Building Department at 360 South County Road, (561) 838-5431, are the two offices named on it.
Why small repairs are not exempt from the construction rules
The most common scheduling mistake is assuming that the season rules cover big projects and leave touch-up work alone. The definition in sec. 42-199(a) does not support that reading.
Construction work means “work of a physical nature requiring a permit in accordance with Chapter 18” and/or “operating or permitting the operation of any tools or equipment used in construction, drilling or demolition work,” including the machinery listed in sec. 42-198(a). Two separate tests sit inside that sentence. A job is construction work if it needs a permit. It is also construction work if it uses construction, drilling or demolition tools, permit or not.
So a two-day job to replace a cracked set of pool deck pavers with a cut-off saw is construction work. So is drilling new anchors for a gate, grinding a stucco patch, or sanding a floor. Re-hanging pictures or swapping a light fixture with hand tools probably is not, though an electrical change that needs a permit would be. The code gives one narrower category, quiet interior work, defined as construction work that is quiet in nature and limited to indoor activity, and that category is the only thing allowed between 8:00 and 9:00 a.m. on a winter weekday.
Landscaping splits along a similar line. The Town treats routine lawn maintenance, such as mowing, trimming, irrigation and yard waste removal, under its own schedule, while the lawn maintenance sheet tells contractors that “construction site or landscaping installation work” follows the construction hours (Town of Palm Beach, Working Hours for Lawn Maintenance, rev. July 16, 2026). New hedges, a replanted entry court or new sod for listing photos are installation work, not maintenance.
The table below sorts common pre-listing jobs by the Town step required and the rule that sets the timing. It is a planning aid built from the Town Code and the Town’s administrative review guide, not a permit determination. The Building Division decides whether a specific scope needs a permit.
| Pre-listing job | Town step before work | Timing rule that bites | Best window |
|---|---|---|---|
| Roof replacement | Administrative review (Table D) and building permit; ARCOM if the materials or appearance change significantly (sec. 18‑175) | Winter hours; tear-off noise not before 9:00 a.m. | Summer, finished by October 31 |
| Window and door replacement | Administrative review (Table E) with numbered openings and product approvals, plus building permit | Winter hours; deliveries not on summer Saturdays | Summer, or winter weekdays with lead time |
| Pool resurfacing with chipping hammers | Building permit | Jackhammers banned November 1 to April 30 (sec. 42‑198(a)(4)) | Summer only for the chipping phase |
| Driveway, patio or pool deck replacement | Administrative review (Table K) and permit | Removal often uses jackhammers or heavy equipment | Summer |
| Generator, condenser or pool equipment | Administrative review (Table J); neighbor consent form inside side or rear setbacks | Winter hours | Either season, allow for consent |
| Fence, wall or gate | Administrative review (Table I); neighbor consent inside setbacks | Winter hours | Either season |
| Landscape renovation | Administrative review (Table L) when altering plans or open space | Installation follows construction hours | Early fall for planting before photos |
| Kitchen or bath tear‑out | Building permit | Interior demolition in winter only if demolition and debris removal finish in three days or less (sec. 18‑112) | Summer, or a tightly staged winter demo |
| Exterior repaint, same color | Color review only for commercial or Landmarks properties (Table F); confirm permit status | Hours apply when power tools or sprayers run | Either season, weekdays in winter |
| Dock or seawall pile work | Town permit plus state and federal approvals | Dredges and hammer-driven pile drivers banned in winter | Summer only |
Table F of the administrative review guide limits paint color review to commercial buildings and buildings under the Landmarks Preservation Commission’s purview (Town of Palm Beach, Administrative Review Guide, version September 23, 2026). Whether a repaint or other finish work needs a building permit at all is a Building Division decision. Send the Building Division a short written scope that names the surfaces, the products and any stucco, wood or metal repair under the paint, and keep its written answer in the listing file. A buyer’s inspector or attorney may ask whether the work was permitted, and a written answer settles the question quickly. Even where no permit is needed, a crew running a pressure washer or an airless sprayer is operating equipment, and the safer plan is to keep that crew inside the construction hours.
The winter machinery and demolition bans
Hours limit when work happens. Two other sections decide whether some work can happen at all between November and May.
Sec. 42-198: the equipment list
From November 1 through April 30, no one may operate dredges, hammer-driven pile drivers, gasoline, diesel or steam engines run in a way that emits offensive odors or noise, dry sandblasting machines and jackhammers, or “any other class of machinery or appliance” that would make the enjoyment of property in the Town less agreeable (Town Code sec. 42-198). Only the Town Council can grant an exception, and only when it finds the operation would not be overly offensive to nearby residents. Essential Town services and emergency work are exempt.
The catch-all clause is the one sellers underestimate. A concrete saw, a large chipper or a skid steer is not named in the list, yet each can fall under the fifth category if it disturbs neighbors, and a code officer’s view on site will matter more than a contractor’s reading of the list. The practical rule is to move anything loud and mechanical into the summer window.
Some common pre-listing jobs depend on the banned list directly. Pool resurfacing usually starts by chipping off the old finish. Removing a tile or concrete pool deck often uses jackhammers. Restoring coral stone or keystone by sandblasting is out. Replacing dock piles with a hammer-driven rig, or any dredging at a waterfront lot on Lake Worth Lagoon, waits for May. Those are not quick-fix items. Each can push the full job, including the quiet finish phase, into the following summer if the noisy phase misses October 31.
Sec. 18-112: demolition
From November 1 to April 30, demolition of structures is prohibited and the Town issues no demolition permits (Town Code ch. 18). Interior demolition is allowed in that period only if the demolition and the removal of its debris are completed in three days or less. The section was last amended by Ordinance No. 15-2026 on May 13, 2026.
Exceptions run through the Town Council. The council may allow demolition of accessory structures it finds will not create a nuisance, or demolition in an emergency. A waiver application requires notice filed with the Town at least 45 days before the council meeting and notice to every owner within 300 feet listed with the property appraiser. In calendar terms, a seller who decides in mid-November to remove a failing cabana before listing is looking at a council date in January at the earliest, with no assurance of approval.
For a full or major demolition outside the winter period, sec. 18-114 adds its own sequence: a bond or letter of credit, approved erosion control, parking, screening and truck logistics plans, and an affidavit that owners within 300 feet received notice no less than 14 and no more than 30 days before the demolition. That notice window alone means a summer demolition has to be planned at least two weeks before the machines arrive.
Sellers weighing whether a buyer will keep or replace the house should read the site’s guide to selling a Palm Beach estate when preservation and redevelopment are both on the table. If the likely buyer plans to tear down, demolishing an accessory structure yourself is rarely worth the winter calendar risk.
Counting the working days in the 2026 to 2027 season
The question a seller actually needs answered is not “what are the rules” but “how many days does my contractor have.” We counted them.
Method: every calendar day from November 1, 2026 through April 30, 2027; Saturdays and Sundays removed under sec. 42-199(b); Town-observed holidays removed from the Town holiday sheet revised July 16, 2026 (Veterans Day November 11, November 25, Thanksgiving November 26, November 27, Martin Luther King Jr. Day January 18, 2027 and Presidents’ Day February 15, 2027); and December 24, 2026 through January 1, 2027 removed under Ordinance No. 7-2025. The count assumes no weather days, no inspection delays and no Council resolution changing the hours. It is our analysis, not a Town publication.
| Month | Calendar days | Weekdays | Permitted construction weekdays | Days lost to holidays and the year-end ban |
|---|---|---|---|---|
| November 2026 | 30 | 21 | 17 | 4 (Nov 11, 25, 26, 27) |
| December 2026 | 31 | 23 | 17 | 6 (Dec 24, 25, 28, 29, 30, 31) |
| January 2027 | 31 | 21 | 19 | 2 (Jan 1, Jan 18) |
| February 2027 | 28 | 20 | 19 | 1 (Feb 15) |
| March 2027 | 31 | 23 | 23 | 0 |
| April 2027 | 30 | 22 | 22 | 0 |
| Total | 181 | 130 | 117 | 13 |
Source: Jeannie Jacobson, REALTOR®, analysis of Town of Palm Beach Code sec. 42-199 and the Town holiday sheet revised July 16, 2026.
Two findings stand out. First, November and December together offer 34 working days, about the same as a summer month and a half once summer Saturdays are counted. A job that a contractor quotes at “six weeks” in August can take ten calendar weeks if it starts in mid-November. Second, the two weeks around the holidays are the exact weeks many owners arrive on the island and want the house photographed for a January launch. Between December 23 and January 4 there is no construction day at all.
Compare the window that is still open as this guide is reviewed. From October 9 through October 31, 2026 the summer schedule still applies, with 16 weekdays and 4 Saturdays. That is the last stretch in 2026 when a crew can run a jackhammer, pour concrete on a weekday morning at 8:30, or demolish a structure with a permit.
The summer of 2027 is the next open window. May 1 through October 31, 2027 contains 126 weekdays after the four federal and Town holidays in that span, plus 26 Saturdays outside Juneteenth. The hours on those days will depend on whatever the code and any Council resolution say in 2027.
Building the schedule backward from a Palm Beach listing date
Start with the date the house should be on the market, fully photographed, and work back. Each step below names the Town office or rule that controls it. Durations that depend on the Town’s review queue or a contractor’s lead time are left for the seller and the contractor to fill in, because the Town does not publish review turnaround times.
Fix the launch date and the photo date
Photography should follow the last exterior work, the last landscape installation and the removal of any construction screening. In season, the photo day itself needs to land on a day the house looks finished, with no crew on site. Choose the photo date first; the listing date follows it by however long the marketing materials take.
Set the final inspection date before the photo date
Minor permits must pass final inspection within 12 months of issuance (sec. 18-238), but a seller wants the final passed well before a buyer’s permit search, not merely within the year. Inspections are requested through the Town’s Citizen Access Portal, known as EPL. Leave room for a failed inspection and a re‑inspection.
Place the noisy phases before November 1
Anything that uses jackhammers, sandblasting, pile drivers, dredges or demolition must be finished by October 31, or it waits until May 1. The quiet finish phases, such as interior paint, trim and fixture installation, can continue on winter weekdays.
Back out the December 24 to January 1 closure
If the work runs through December, assume nothing happens from December 24 through January 1 and that crews may not return at full strength on January 4. Do not plan a final inspection or a photo shoot in that span.
Back out permit issue and any review approval
Administrative review applications go to the Planning, Zoning and Building Department and can be filed online through EPL, and the guide warns that a separate building permit may also be required. Ask the contractor when, from experience, the permit is likely to issue, then add a buffer for comments and resubmittal.
Back out ARCOM if the scope needs it
The Architectural Commission meets monthly (sec. 18-174), with filing deadlines on the Town’s Development Review Calendar. Hearings listed on the Town calendar include September 23 and October 28, 2026. A project that needs a full ARCOM hearing cannot start in time for a January listing if it is not already on an agenda. Series article 01 covers ARCOM and Landmarks review as a selling issue.
Back out contractor selection and product lead time
Impact windows, doors and specialty roofing often have long manufacturing lead times. Product approvals have to be in the administrative review package (Tables D and E of the guide), so the product choice is made before the application, not after.
Here is how that looks for a hypothetical target of a fully photographed house on February 1, 2027. The dates show the order of steps, not a promised outcome.
| Step | Latest sensible date | Rule behind it |
|---|---|---|
| Photography, no crew on site | Late January 2027 | Screening removed, landscape installed |
| Final inspections passed | Mid-January 2027, after the January 4 restart | Sec. 18-238; inspection scheduling in EPL |
| No work | December 24, 2026 to January 1, 2027 | Sec. 42-199(b), Ord. No. 7‑2025 |
| Quiet and finish work, weekdays only | November 2 to December 23, 2026 | Winter hours, sec. 42‑199(b) |
| Jackhammer, sandblasting and demolition phases complete | October 31, 2026 | Secs. 42-198 and 18‑112 |
| Permits issued, products ordered | Already past for most scopes if not done by early October | Administrative review and building permit |
An owner reading this in October 2026 with no permit in hand should be realistic. For a February 2027 launch, the scopes that still fit are quiet interior work, painting and weekday finish work that need no machinery from the banned list. The rest becomes either a summer 2027 project or an item that the pricing and the disclosure account for.
Town review steps that set the start date
On the island, the start date of a pre-listing project is set less by the contractor than by the Town’s review path. The Planning, Zoning and Building Department at 360 South County Road handles both design review and building permits.
Administrative review: the staff-level path
Many exterior changes go through administrative review rather than a public ARCOM hearing. The Town’s Administrative Review Guide lists the categories and the documents each needs: freestanding accessory structures such as pergolas, small additions not visible from the right of way, building alterations such as gutters and decorative shutters, roof replacement, window and door replacement, paint color for commercial or Landmarks properties, awnings, hurricane shutters, fences and gates, mechanical equipment including generators up to 100 kW, hardscape such as driveways, patios and pools, landscape changes, landscape lighting and statuary (Administrative Review Guide, version September 23, 2026).
Several requirements in that guide add calendar time a seller may not expect. Window and door replacement needs a floor plan with numbered openings, photographs keyed to those numbers and product sheets showing size, material, style, finish and lite pattern. Fences, walls, gates, mechanical equipment and landscape work inside side or rear setbacks need a neighbor consent form. A property in a condominium building needs a condominium association approval letter. Each of those depends on someone other than the owner.
ARCOM: the monthly hearing
Larger exterior changes, and reroofing that significantly changes materials or appearance, need Architectural Commission approval before a permit can issue (sec. 18-175). The commission meets monthly. An approval expires 24 months from the written decision unless a building permit has been obtained (sec. 18-203), which means a seller can secure an approval that a buyer may later use, within that window. Whether a pending or approved plan adds value is a pricing question covered in series article 04 on pricing a Palm Beach home by section of the island.
The portal and the permit record
Permit applications can be filed online through EPL at any hour, while in-person submittals end at 4:00 p.m. on weekdays, according to the Town’s permit instructions (Town of Palm Beach, Building Permits). Permits issued before April 1, 2024 that begin with “B” sit in the older EDEN system. A buyer’s agent or attorney may search both, which is why the age of a permit and the system it lives in matter in section 9.
Florida law sets time frames for local permit review under sec. 553.792, Florida Statutes, and the Town processes permits under the Florida Building Code as amended by its own administrative amendments (Town Code sec. 18-234). The Town does not publish a turnaround figure for residential reviews. A seller should ask the contractor for a written estimate of the permit date and treat it as an estimate.
Site rules that follow the house onto the market
A house under construction on the island looks different from a house under construction in most towns, and the Town Code is the reason. Several of those rules affect how a property shows if the listing goes live before the work is done.
Construction screening
Sec. 18-353 requires construction sites to be secured and screened with fencing, walls and dense landscaping that prevent public viewing of the project, from the time earth is disturbed or materials are placed until fixtures and final landscaping are complete. Barriers visible from the right of way must be six to 12 feet high, one shade of green or black, with chain link carrying mesh of at least 90 percent opacity, and no signage or decoration. The barrier may go up no sooner than ten days before construction starts, and only after the permits are issued. Fences are not required on a side facing the Atlantic Ocean or the Intracoastal Waterway unless the director asks for one.
For a seller, that is a listing photography problem. A green mesh fence across the front of the lot is in every street-side photo until the work is substantially complete and the director approves removal. Exterior painting, cosmetic material repairs, landscape improvements, plant removal and work inside an existing opaque wall are exempt from the barrier requirement, which is one more reason to keep pre-listing work to those categories when the calendar is tight.
Staging, trucks and parking
Projects that need major ARCOM or Landmarks approval must include a construction staging and truck logistics plan showing parking, material storage, deliveries, dumpsters, portable toilets and the truck route across the island, including the roads and bridges used (sec. 18-86). Smaller jobs still face the Town’s construction parking rules: crews park on site where possible, and a contractor who cannot fit everyone may apply for permits for up to three construction vehicles on the street, according to the Town’s permit application checklist (Town of Palm Beach, Permit Application Checklist).
Strikes, stop work orders and management agreements
Violations of the construction hours or the site maintenance rules count as strikes under the Town’s “3 Strike Rule” in its Right-of-Way Manual (secs. 18-351 and 18-352). Three strikes at one site lead to a stop work order, and the permit application checklist notes that work does not resume until the Town Council reinstates the permit, with the Council meeting monthly. Since Ordinance No. 008-2025, any adjudicated strike, adjudicated code violation or stop work order also requires the owner and contractor to sign a construction management agreement with the Town setting completion time, hours, transportation routes and neighbor notice (sec. 18‑355).
A stop work order on a property that is about to list is more than a delay. It is a public record that a buyer’s due diligence can find, and it may raise questions the seller then has to answer. Choose a contractor who works on the island regularly and ask directly whether they have had strikes on other Town of Palm Beach jobs.
Permit clocks and what a buyer’s search will show
Every permit issued in the Town of Palm Beach carries a deadline, and the deadline becomes part of the sale if it is still running at listing.
Sec. 18-238 sets the clock for minor construction, meaning work under the major threshold. Minor work must be completed and pass final inspection no later than 12 months from issuance. For work on single-family dwellings, the deadline is 12 months or the effective date of the next edition of the Florida Building Code, whichever is later. The building official can extend for up to 90 days if the request is filed at least 15 calendar days before the completion date and the extension fee is paid. If a permit expires first, it can be reactivated for a fee. If the work is not finished in time, the permit is revoked and the failure counts as evidence that the project was suspended or abandoned.
Major construction is defined in sec. 18-232 as improvements valued at $250,000 or more, and smaller permits on the same project are added together once the total reaches that figure. Major projects follow the schedule in sec. 18-237, which sets maximum times by square footage under roof. Extensions beyond that schedule go to the Town Council, require a request filed at least 30 days before the permit expires with mailed notice to neighbors within 300 feet, and, if granted, carry a fee of one percent of the value of the remaining unfinished work under sec. 18-240. Town staff may grant an administrative extension of up to 90 days.
What does that mean for a seller? Three situations come up.
- Work finished, permit still open. The most avoidable problem. Request the final inspection, confirm it passed in EPL, and keep the record for the listing file. The site’s guide to open permits when selling a house explains how buyers and title companies treat open permits.
- Work in progress at listing. A buyer will ask who finishes the job, under whose permit, before or after closing, and what happens if the permit clock runs out. The answers belong in the contract, and a real estate attorney should draft them.
- Major project near its schedule limit. A buyer inherits a Council extension process with neighbor notice and a fee tied to the remaining value. That is a pricing item, and it should be disclosed early rather than discovered.
Older permits deserve a look too. Because permits issued before April 1, 2024 live in EDEN and later ones in EPL, a seller should pull both and reconcile them against the work actually done in the house. Doing that in the summer, before any listing date is set, leaves time to close out an old permit with summer hours available if a correction is needed.
Condominium and co-op apartments on the island
For an apartment owner in the Town of Palm Beach, the Town calendar is often the looser of two calendars. The building’s own rules may be stricter.
The Town Code acknowledges this directly. Sec. 18-237 allows the major construction schedule to be extended for individual condominium units that are required by condominium rules to stop work during the season as the association defines it, by the number of months the rules require work to stop. Sec. 18-239 also refers to multifamily properties where construction is limited to no more than seven months a year through association restrictions. In other words, the Town expects many buildings to close renovation for part of the year, and it builds the permit clock around that.
There is one exception that runs the other way. Under sec. 42-199(e)(4), quiet interior work is allowed on winter Saturdays from 9:00 a.m. to 5:00 p.m. for multi-family properties south of Sloan’s Curve that are not on Ibis Isle, if the association board approves Saturday work and a copy of the board’s approval letter is on record with the Town. Owners in other parts of the island do not have that option.
For a seller, the order of questions is:
- Do the association’s rules close renovation for part of the year, and on what dates? Ask the manager for the current rules and regulations in writing, because renovation months and daily hours differ from building to building and can be stricter than the Town’s.
- Does the building require board approval of contractors, insurance certificates or a deposit before work starts?
- Will the board issue the approval letter that administrative review requires for a unit in a condominium building?
- If the building is south of Sloan’s Curve and not on Ibis Isle, has the board approved winter Saturday quiet work and filed the letter with the Town?
Co-op buildings add a buyer approval process that has its own calendar. Series article 02 covers selling a co-op apartment in Palm Beach, including board timing. A seller planning a kitchen update in a co-op should know that the work calendar and the board calendar both run through the same winter months.
Worth Avenue, shutters and the lawn crew
Three smaller rules catch sellers off guard, each tied to a specific part of the island or a specific season.
Residences in the C-WA zoning district
Construction in the C-WA zoning district, the Worth Avenue commercial district, is permitted only from May 1 to October 31 under sec. 42-199(d). The Town’s sheet states it plainly: “NOV 1 thru APR 30 – NO WORK.” Sec. 18-237 lets residential projects in the district extend the construction schedule to account for that closure. An owner of a residence above or near Worth Avenue who wants work done before a winter listing has one window, and it closes October 31.
Storm shutters
Sec. 18-1010 bars one- and two-family dwellings and townhouse buildings up to three stories from keeping storm shutters or other hurricane protection closed over windows or doors from December 1 to April 30, except in storm conditions. From May 1 to November 30, closed shutters are allowed and encouraged for houses. An owner who closes the house for the summer and lists from out of state should arrange for shutters to be opened by December 1 regardless of the listing date, and earlier if photographs or showings are planned. The site’s guide to selling a home from out of state covers access, keys and remote signing. If the house still has accordion or panel shutters rather than impact glass, the guide on whether impact windows add value helps frame that decision, though the timing of any replacement on the island follows the rules in this article.
Lawn maintenance versus landscape installation
Routine lawn maintenance has its own winter schedule: weekdays from 8:00 a.m. to 5:00 p.m., arrival from 7:30 a.m., quiet maintenance only from 8:00 to 9:00 a.m., no site noise before 9:00 a.m., and no work on Saturdays, Sundays or federal holidays. On the Friday after Thanksgiving, Christmas Eve and New Year’s Eve, lawn maintenance is allowed from 9:00 a.m. to 2:00 p.m. In summer, Saturday lawn work is limited to tree and hedge trimming from 9:00 a.m. to 3:00 p.m. (Town lawn maintenance sheet, rev. July 16, 2026). Any bucket truck or lift used in the right of way needs a right-of-way permit.
For listing preparation, that means the regular crew can keep hedges sharp through the winter on weekdays, including on the three short days around the holidays, but new planting is installation work under the construction hours. Plant early enough in the fall for new material to settle before photographs. The site’s guide to staging a house to sell covers the interior side of that preparation.
Choosing between an in-season launch and a summer finish
Once the work calendar is clear, the decision becomes a trade-off: list in season with the house as it is, or finish the work in summer and list later.
The argument for an in-season launch rests on the assumption that more qualified buyers are on the island between January and April. Public records can test part of that assumption. The Palm Beach County Property Appraiser’s Sales Search lists recorded sales by municipality, and the table below counts every qualified single-family sale in the Town of Palm Beach by the month of the sale date shown in the record.
| Month of sale date | October 2024 to September 2025 | October 2025 to September 2026 |
|---|---|---|
| October | 2 | 10 |
| November | 7 | 1 |
| December | 7 | 12 |
| January | 9 | 10 |
| February | 8 | 10 |
| March | 7 | 17 |
| April | 12 | 22 |
| May | 11 | 13 |
| June | 11 | 16 |
| July | 1 | 7 |
| August | 2 | 9 |
| September | 6 | 6 |
| November to April total | 50 | 72 |
| May to October total | 33 | 61 |
| Year total | 83 | 133 |
Query behind the table: Palm Beach County Property Appraiser Advanced Sales Search, Residential tab, search by municipality “Palm Beach”, property use code 0100 (single family), qualified sales only, sale dates October 1, 2024 through September 30, 2026, no price or size limits, queried October 8, 2026 (Palm Beach County Property Appraiser, Sales Search). The search returned 216 sales, and no two of them share a date, price and buyer, so each row is one transaction. The Property Appraiser notes that some transactions reach its records late, so the most recent months may still grow.
Three readings follow. Over the two years, 122 of the 216 sales carry a sale date between November and April, and 94 carry one between May and October. The busiest single month was April 2026, with 22 sales, followed by March 2026 with 17. And the summer was not empty: May and June together recorded 22 sales in 2025 and 29 in 2026.
These are closings, not contracts. A sale dated in May may have been agreed in March, so the public record shows when buyers finished paying, not when they decided. Three figures that would sharpen the decision come only from the MLS, and the listing agent can pull them from an MLS export of Town of Palm Beach single-family sales for the same period. Pending contracts grouped by contract date show when buyers commit. Median days from listing to contract in each half of the year show how long an unfinished house might wait. The ratio of sale price to last list price in each half shows how much room buyers negotiated. If winter contracts are clearly more frequent and faster, an unfinished house listed in January competes in a stronger buyer pool but must be priced for the work a buyer will inherit. If the gap is small, finishing the work in summer 2027 and listing in the fall may cost little in buyer activity and gain a cleaner presentation. The answer will differ between the North End, the midtown estate section and the South End, which is why series article 04 treats pricing by section of the island separately.
Some practical observations hold regardless of the data.
- A buyer in season who wants to renovate faces the same calendar. If the buyer closes in March, the noisy phases of the buyer’s own project cannot start until May 1. Sellers of houses that need work can point to that calendar honestly; a buyer who closes before summer has the full summer window ahead.
- Credits and price reductions for unfinished work should be based on written contractor estimates, not guesses. Commission and other costs of sale are negotiable and should be modeled separately from repair credits.
- A permit in progress is not a reason to delay disclosure. Florida disclosure obligations apply regardless of season, and the site’s guide to seller disclosure requirements explains the general framework.
- Approved plans can be part of the marketing, within the 24-month life of an ARCOM approval under sec. 18-203, when a buyer is likely to want the change the seller had approved.
The site’s hub on how to sell a luxury home over $1 million covers the broader listing process, and the Palm Beach County luxury listing page describes the listing services available.
What Sellers Say About Working With Jeannie Jacobson
These reviews do not name a town and are not from Palm Beach sellers. They describe sellers’ experience with listing timing and effort.
“…We were with another realtor for 6 months with no activity. Once that was up, we met with Jeannie and explained to her the desperation of our situation and she had the house sold in 5 days. It was more than we could have hoped for…”
Andrew, Google review
“…She was professional, punctual and really worked hard to get my property sold. It sold in record time…”
Tina Shaw, Google review
This guide is general information about Town of Palm Beach rules as posted in October 2026. It is not legal, tax, engineering or financial advice. Construction hours, holiday dates and permit rules change by ordinance and by Council resolution. Confirm current requirements with the Town of Palm Beach Planning, Zoning and Building Department before scheduling work, and consult a licensed contractor and a Florida real estate attorney about permits and contract terms for your property.
Frequently Asked Questions
The winter construction season runs from November 1 through April 30 under Town Code sec. 42-199(b). Ordinance No. 021-2025, adopted October 14, 2025, moved the start earlier; before that, reporting on the proposal described a start on the first Monday after Thanksgiving. Contractors who work across the county may still plan around the old date, so confirm in writing that noisy phases finish by October 31.
No, with one narrow exception. From November 1 to April 30, construction work is prohibited on Saturdays and Sundays. The exception allows quiet interior work from 9:00 a.m. to 5:00 p.m. on Saturdays at multi-family properties south of Sloan’s Curve, not on Ibis Isle, where the association board has approved Saturday work and its approval letter is on record with the Town.
No. Ordinance No. 7-2025 prohibits construction work from December 24 through January 1. For the 2026 to 2027 season, the Town’s holiday sheet shows no construction from Thursday, December 24, 2026 through Friday, January 1, 2027, so the first working day after the break is Monday, January 4, 2027. Routine lawn maintenance is allowed on Christmas Eve and New Year’s Eve from 9:00 a.m. to 2:00 p.m.
Often, yes. Sec. 42-199(a) defines construction work as work requiring a permit under Chapter 18 or work that operates tools or equipment used in construction, drilling or demolition. A short job with a saw, grinder or drill meets the second test even without a permit. Only quiet interior work is allowed between 8:00 and 9:00 a.m. on winter weekdays, and nothing is allowed on winter weekends.
A roof replacement can proceed on winter weekdays within the hours if it is permitted and uses no equipment banned under sec. 42-198. It needs administrative review under Table D of the Town guide and a building permit, and ARCOM approval if the new roof significantly changes materials or appearance. Tear-off is noisy, so no work before 9:00 a.m., and the December 24 to January 1 closure will interrupt it.
Demolition of structures, such as a pool house or cabana, is prohibited from November 1 to April 30 and the Town issues no demolition permits in that period, unless the Town Council grants an exception after 45 days’ notice and notice to owners within 300 feet. Interior demolition, such as a kitchen tear-out, is allowed in winter only if the demolition and debris removal are completed in three days or less.
For minor construction, work must pass final inspection within 12 months of issuance, or for single-family dwellings by the later of 12 months or the next Florida Building Code edition’s effective date (sec. 18-238). The building official can extend up to 90 days on a request filed 15 days before the deadline. Major projects of $250,000 or more follow a longer schedule by square footage, with extensions decided by the Town Council.
Construction in the C-WA zoning district, which covers Worth Avenue, is allowed only from May 1 to October 31 under sec. 42-199(d), with no work at all from November 1 to April 30. Sec. 18-237 lets residential projects in that district extend their construction schedule to account for the winter closure. An owner there who wants work done before a winter listing must finish it by October 31.
Not between December 1 and April 30. Sec. 18-1010 prohibits one- and two-family dwellings and townhouse buildings up to three stories from keeping storm shutters or other hurricane protection closed over windows or doors in that period, except in storm conditions. From May 1 to November 30 they may stay closed. An owner who is away should arrange for them to be opened before photographs and showings.
It depends on the scope, the permit status and how the price accounts for the remaining work. Listing in season with work pending means construction screening may appear in photos and a buyer will ask who finishes the work under which permit. Finishing in summer and listing later gives a cleaner presentation. Compare both with a written pricing analysis and contractor estimates, and have an attorney draft any completion terms.
The Planning, Zoning and Building Department at 360 South County Road, (561) 838-5431, handles permits and construction hours, and the Code Enforcement Department at 345 South County Road, (561) 227-7080, enforces them. The Town posts a working hours sheet and a holiday sheet that are revised when ordinances or resolutions change; the version current in October 2026 is dated July 16, 2026.
Set the listing date first, then the work calendar
Bring the scope, the contractor’s quote and your preferred launch month. The first step is putting the Town of Palm Beach closed days, the October 31 cutoff for noisy work and your permit status on one calendar, then pricing the house for the condition it will be in on that date.
Jeannie Jacobson, REALTOR®, RE/MAX Gold, (772) 877-0268, English and Spanish
Sources
- Code of Ordinances, Chapter 42, Article V, Noise, secs. 42-196 to 42-202 (Supplement 30, Update 2, online October 5, 2026), Town of Palm Beach via Municode, https://library.municode.com/fl/palm_beach/codes/code_of_ordinances?nodeId=PTIICOOR_CH42EN_ARTVNO (accessed October 2026)
- Code of Ordinances, Chapter 18, Buildings and Building Regulations, secs. 18-86, 18-112, 18-114, 18-174, 18-175, 18-201 to 18-203, 18-232 to 18-240, 18-351 to 18-355, 18-1010, Town of Palm Beach via Municode, https://library.municode.com/fl/palm_beach/codes/code_of_ordinances?nodeId=PTIICOOR_CH18BUBURE (accessed October 2026)
- Advanced Sales Search, Palm Beach County Property Appraiser, query by municipality “Palm Beach”, use code 0100, qualified sales only, October 1, 2024 to September 30, 2026, https://pbcpao.gov/AdvSearch/SalesSearch (accessed October 2026)
- Holiday Dates that Impact Construction and Lawn Maintenance; Working Hours for Construction; Working Hours for Lawn Maintenance (rev. July 16, 2026), Town of Palm Beach Code Enforcement and Planning, Zoning and Building Departments, https://www.townofpalmbeach.com/DocumentCenter/View/116/Construction–Landscaping-Working-Hours (accessed October 2026)
- Administrative Review Guide (version September 23, 2026), Town of Palm Beach Planning, Zoning and Building Department, https://townofpalmbeach.com/DocumentCenter/View/27903/ADMIN-REVIEW_GUIDE_092526 (accessed October 2026)
- Building Permits and Business Tax Receipts, Town of Palm Beach, https://townofpalmbeach.com/1295/Building-Permits-and-Business-Tax-Receip (accessed October 2026)
- Permit Application Checklist, Town of Palm Beach Building Division, https://www.townofpalmbeach.com/DocumentCenter/View/361/Application-for-Construction-Permit- (accessed October 2026)
- Planning, Zoning and Building Department, FAQs on development review deadlines and hearing dates, Town of Palm Beach, https://townofpalmbeach.com/FAQ.aspx?QID=257 (accessed October 2026)
- Architectural Commission meeting calendar entries, Town of Palm Beach, https://www.townofpalmbeach.com/Calendar.aspx?EID=3248 (accessed October 2026)
- “A season extended: Town Council tackles construction, parking, and traffic during winter season,” Palm Beach Daily News via Yahoo News (secondary), https://news.yahoo.com/season-extended-town-council-tackles-090214114.html (accessed October 2026)
- Section 553.792, Florida Statutes, Building permit application to local government, Florida Legislature, http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0500-0599/0553/Sections/0553.792.html (accessed October 2026)